The following schedule identifies major steps in the planning process. The schedule will be adjusted as necessary throughout the duration of the project.

 

January 2014Project Kick-off Meeting with City Staff
February-March 2014Stakeholder Interviews
March-May 2014Baseline Studies and Analyses
May-August 2014City Review of Baseline Studies and Analyses
September-October 2014Preliminary Land Use and Design Plan
December 2014Steering Commitee #1: Preliminary Land Use & Design Plan
December 2014Community Workshop #1: Preliminary Land Use & Design Plan
January 2015Community Workshop #2: Visioning and Preliminary Design Plan
Winter-Spring 2015Refined Preliminary Land Use and Design Plan
Summer 2015Steering Committee Meeting: Refined Land Use and Design Plan
Fall 2015-Winter 2016Preparation of Administrative Draft Specific Plan
Spring-Summer 2016City Review of Administrative Draft Specific Plan
Fall 2016Preparation of Public Review Draft Specific Plan
December 6, 2016Planning Commission Study Session: Public Review Draft Specific Plan
December 7, 2016Community Workshop #3: Public Review Draft Specific Plan
January 2017Preparation of Public Hearing Draft Specific Plan
March 2017Planning Commission Hearing
March 2017 City Council Hearing (continued to June 2017)
May 2017Community Workshop #4: Public Hearing Draft Specific Plan
June 2017City Council Hearing
July 2017Preparation of Final Plan